Home / MAJOR PROJECTS

MAJOR PROJECTS

Ports in North Area
Quang Ninh

Project

Total investment

Implementation

Dredging access channel to -10m US$ 10 million End of 2004
Upgrading Cai Lan wharf No. 1 to -12m depth alongside for 40,000 DWT vessels. US$ 1.3
million
Early 2005
Building 3 deep water wharves, Cai Lan No.2, 3, and 4 of -13m depth alongside for 40.000 DWT vessels US$ 140 million End of 2005
Cam Pha

Project

Total investment

Implementation

Expanding 250m of wharf and dredging wharf water front to -10.5m deep US$ 10
million
2002-2005(50% of the project being completed.)
Hai Phong

Project

Total investment

Implementation

Port rehabilitation and upgrading, Phase II US$ 126.0million 2004-2008
Dinh Vu Port, Phase II US$ 12.7million 2005-2007, Pre-FS initiated
Ben Got-Lach Huyen lighterage area US$ 1.6million 2004-2005. FS initiated.
Cua Cam

Project

Total investment

Implementation

Rehabilitation and upgrading of wharf No.1 US$ 0.13
million
2004
Procurement of 1 shorecrane US$ 0.1
million
2004
Doan Xa Procurement of handling equipments and means of transportation being implemented in 2004 with total investment capital estimated at US$ 2.3 million
Vat Cach

Project

Total investment

Implementation

Rehabilitation and upgrading 61m of wharf US$ 0.3
million
Completed and operational in March 2004
Procurement of 2 shorecranes (01 tower crane) and construction of 5,000m2 warehouses US$ 0.4
million
Ports in Central Area
Thanh Hoa

Project

Total investment

Implementation

Construction of Nghi Son wharf No.2 225m long for 30,000 DWT vessels US$ 17.1million estimated 2004-2008
Procurement of tugboat, shorecrane, and forklift truck for Nghi Son terminal US$ 0.4
million
Nghe Tinh

Project

Total investment

Implementation

Upgrading and expansion of Cua Lo terminal US$ 12
million
For completion in 2003
Vung Ang

Project

Total investment

Implementation

Building wharf No.2 US$ 33.2
million
2004-2008
Quang Binh

Project

Total investment

Implementation

Upgrading and expansion of Gianh terminal, phase II, to increase the handling capacity of 800,000 MTs/Year and to accommodate vessels of 5,000 DWT US$ 5.1
million
2004-2007
Cua Viet

Project

Total investment

Implementation

Precurement of 1 shore crane with 40 tons lifting capacity US$ 0.06
million
2004
Upgrading Dong Ha Terminal US$ 0.2
million
2004
Da Nang

Project

Investment capital

Time planning & status implementation

Upgrading and rehabilitation of Tien Sa Terminal US$ 46.0
million
2001-2004
Tien Sa hinterland storage complex US$ 1.8
million
2003-2006
Procurement of tug boat US$ 0.6
million
2004-2005
Procurement of 100T crane US$ 1.5
million
Planned
9 Song Han

Project

Total investment

Implementation

Construction new terminal at Vung Thung-Son Tra and relocation of existing port US$ 4.4
million
2 years. Underway
Ky Ha

Project

Total investment capital

Implementation

Port upgrading and rehabilitation: ugrading wharf for 20,000T container vessels, procurement of 2 1500HP tugboats and 1 70T lifting capacity shorecrane US$ 2.9
million
2004-2005
Ky Ha – Quang Nam

Project

Total investment

Implementation

Upgrading wharf No.2. US$ 3.2
million
2004
Thi Nai

Project

Total investment

Implementation

Upgrading the existing 2000T wharf up to 5000T US$ 1.9
million
2004 – 2006
Ba Ngoi

Project

Total investment

Implementation

Building a jetty berth and storage facility US$ 2.5
million
2004-2010
Nha Trang

Project

Total investment

Implementation

Upgrading and expansion US$ 9.5
million
Phase II completed in 2004.
Qui Nhon

Project

Total investment

Implementation

Building wharf for 30,000 DWT vessels, building open yards and internal roads, dredging access channel US$ 7.2
million
To be completed 2nd quarter, 2004
Precurement of 1 tug boat and handling equipment: shore crane, forklift US$ 2.8
million
2004
Ports in South Area
Ben Dam-Con Dao VT

Project

Total investment

Implementation

Upgrading Con Dao – Vung Tau Terminal US$ 1.8
million
2004
Construction of cold storage at Ben Dam terminal US$ 1.5
million
2005
Construction of Con Dao Tourist Berth US$ 3.2
million
2005
Land rehabilitation to construct yards/warehouses at Ben Dam terminal US$ 1.0
million
2004
Phu My

Project

Total investment

Implementation

Expanding 150m of wharf, building 10,000m2 of warehouses/open yards, and purchasing quayside gantry crane 30 MT lifting capacity USD 10 million 2003-2004
Saigon New port

Project

Total investment

Implementation

Procurement of 3 quayside gantry cranes for handling container, 4 transtainers for stacking container at CY, 2 cranes 200-300T, 3 lifters for 40′ laden containers, 2 lifters for empty containers, 1 tugboat with 2400HP, 1 self-propelled barge for transporting containers, 20 tug masters with 20 trailers for 20’~45′ containers. Construction of 300m wharf, 24,00m2 of warehouses and 70,000m2 of CY at Cat Lai terminal. Investing in projects of port development in the areas of Ba Ria-Vung Tau, Khanh Hoa, and Hai Phong US$ 36.2
million
2004-
Saigon

Project

Total investment

Implementation

Deep water port projects at Cai Mep and Thi Vai in Ba Ria-Vung Tau provinceHiep Phuoc port projectProjects within the conversion plan of existing facilities 2004-
Ben Nghe

Project

Total investment

Implementation

Upgrading and expanding, phase III US$ 0.6
million
Underway
Tan Thuan Dong

Project

Total investment

Implementation

Plan to relocate existing terminal
Rau Qua

Project

Total investment

Implementation

Procurement of handling equipments/facilities. US$ 0.5
million
2004-2005
Procurement of waterway transportion means US$ 0.6
million
2004-2005
Saigon Petro

Project

Total investment

Implementation

Anti-corrosion works US$ 0.3
million
being completed in 2005
Bong Sen

Project

Total investment

Implementation

Building 150 m of wharf No.2 and expanding 50,000 m2 of container open storage US$ 2.5
million
For completion end of 2004
Dong Thap

Project

Total investment

Implementation

Building a new wharf, warehouse/open yard, Sa Dec terminal office US$ 3.2
million
2001-2005
Vinh Long

Project

Total investment

Implementation

Building a material handling wharf at Binh Minh district US$ 0.9
million
2000-2005
My Thoi

Project

Total investment

Implementation

Port upgrading US$ 0.9
million
2003-2005